In the "Task calendar by days" view, tasks are displayed based on their completion dates. Each task appears as a rectangle positioned according to its completion date. If a task has a start date and a completion date, it is displayed as a continuous bar extending from the column with the start date to the column with the completion date. If a task has only a completion date, it is displayed in the column corresponding to that date.

EJ7T3x.png

Settings for "Task calendar by days" list

In a list's settings, you can define which tasks will be displayed in the list, and you can configure various aspects of how they will be displayed: