This type of Planner list lets you manage a schedule for any objects. There's a list of objects on the left-hand side of the schedule, with a calendar grid on the right-hand side: | {{#seo: | ||
|title=Schedule by day | |||
|titlemode=append | |||
|keywords=planfix, Schedule, planner | |||
|description=Schedule by day | |||
}} | |||
This type of [[Types of planner lists | Planner list]] lets you manage a schedule for any objects. There's a list of objects on the left-hand side of the schedule, with a calendar grid on the right-hand side: | |||
Line 12: | Line 18: | ||
*'''Schedule by field''' - allows you to select the field in which objects for the schedule are stored. The following types of fields are supported: | *'''Schedule by field''' - allows you to select the field in which objects for the schedule are stored. The following types of fields are supported: | ||
**List | **[[List]] | ||
**Task | **[[Task (Field type) | Task]] | ||
**Directory entry | **[[Directory entry]] | ||
**Set of directory values | **[[Set of directory values]] | ||
**Contact | **[[Contact]] | ||
**Employee | **[[Employee]] | ||
**Counterparty | **[[Counterparty (custom field)]] | ||
**Group, | **[[Group, employees or contact]] | ||
**List of users | **[[List of users]] | ||
Line 29: | Line 35: | ||
Background color - lets you choose what will affect "busy" blocks (tasks) in the schedule. There are two options: | *'''Background color''' - lets you choose what will affect "busy" blocks (tasks) in the schedule. There are two options: | ||
Set by task status | **Set by task status | ||
Set manually for each object (schedule row) | **Set manually for each object (schedule row) | ||
https://pic.planfix.ru/pf/bP/zsEk2z.png | |||
Display rows - here, you need to add all the objects that will be displayed for the schedule: | *'''Display rows''' - here, you need to add all the objects that will be displayed for the schedule: | ||
https://pic.planfix.ru/pf/rD/tcserF.png | |||
Start date and Due date - "Date" fields that determine the start and end of the "busy" block in the schedule: | *'''Start date''' and '''Due date''' - "Date" fields that determine the start and end of the "busy" block in the schedule: | ||
https://pic.planfix.ru/pf/9R/hxtZDo.png | |||
With "Schedule by day" lists, you can use any "Date" field; you're not limited to just the standard task start and end dates. This widens the scope of how these lists can be used. | With "Schedule by day" lists, you can use any "Date" field; you're not limited to just the standard task start and end dates. This widens the scope of how these lists can be used. | ||
Additional information | ==Additional information== | ||
Dragging objects to and from this kind of list is not currently supported. | *Dragging objects to and from this kind of list is not currently supported. | ||
Within a schedule, blocks can be moved between different rows/objects. | *Within a schedule, blocks can be moved between different rows/objects. | ||
Only users with paid Planfix accounts can use Schedule by day Planner lists. | *Only users with paid Planfix accounts can use '''Schedule by day''' Planner lists. | ||
==Go To== | ==Go To== |
Latest revision as of 14:45, 2 October 2024
This type of Planner list lets you manage a schedule for any objects. There's a list of objects on the left-hand side of the schedule, with a calendar grid on the right-hand side:
By selecting the desired date range to the right of a specific object, you can create a task that will be displayed as a "busy" block for the specified dates. When you do this, you can create a visual system for reserving tasks for each object, and at the same time build a workload calendar.
Configuring a schedule by day
This kind of planner list has several special options in its settings:
- Schedule by field - allows you to select the field in which objects for the schedule are stored. The following types of fields are supported:
When using fields that contain directory entries, you can specify additional directory fields to display in the schedule table:
- Background color - lets you choose what will affect "busy" blocks (tasks) in the schedule. There are two options:
- Set by task status
- Set manually for each object (schedule row)
- Display rows - here, you need to add all the objects that will be displayed for the schedule:
- Start date and Due date - "Date" fields that determine the start and end of the "busy" block in the schedule:
With "Schedule by day" lists, you can use any "Date" field; you're not limited to just the standard task start and end dates. This widens the scope of how these lists can be used.
Additional information
- Dragging objects to and from this kind of list is not currently supported.
- Within a schedule, blocks can be moved between different rows/objects.
- Only users with paid Planfix accounts can use Schedule by day Planner lists.