In the "Task calendar by days" view, tasks are displayed based on their completion dates. Each task appears as a rectangle positioned according to its completion date:

1.If a task has a start date and a completion date, it is displayed as a continuous bar extending from the column with the start date to the column with the completion date.

2.If a task only has a completion date, it is displayed within the column corresponding to its completion date.

DZwJ72.jpg

Settings for "Task calendar by days" list

In a list's settings, you can define which tasks will be displayed in the list, and you can configure various aspects of how they will be displayed:

Ko8MUJ.jpg

The following options are available: