Overdue task

From Planfix
Revision as of 13:58, 28 July 2023 by Aliona (talk | contribs)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to: navigation, search

A task that hasn't been transferred to "Completed" or "Finished" status by the end of its scheduled completion date becomes overdue. Its name is displayed in red in the user interface:

i0RUep.png

In the task card, the completion date is also displayed in red:

sM5IXl.png

The overdue task is also added to the corresponding list in the Planner:

NlVd7o.png

What to do when a task is overdue?

  • The Assigner should clarify the reasons for the delay with the Assignee, discuss and set a new scheduled completion date. To do this, add a comment to the task and notify the Assignee.
  • The Assignee explains the reason for not completing the task on time and agrees with the Assigner on a new task deadline.