Tracking planned completion dates for tasks with different statuses: Difference between revisions

From Planfix
Jump to: navigation, search
No edit summary
No edit summary
Line 11: Line 11:


   
   
You can change this setting when creating or editing a status.
You can change this setting when [[Adding a new status | creating]] or editing a status.





Revision as of 03:28, 8 April 2020

The attribute Track deadlines for tasks with this status defines whether or not a task with the given status will be considered overdue after the planned completion date set in the task.


fEczk8.png


If Track is selected — which is the default — then if a task has the given status after the planned completion date, the task will have an Overdue flag and will be displayed as such in the interface.


If Don't track is selected, the task will not be overdue if it has the given status after the planned completion date.


You can change this setting when creating or editing a status.