Task status once accepted: Difference between revisions
From Planfix
No edit summary |
|||
Line 15: | Line 15: | ||
https://pic.planfix.ru/pf/je/6yI32T.png | https://pic.planfix.ru/pf/je/6yI32T.png | ||
==Additional information== | ==Additional information== | ||
By default, a task's status is changed to '''In progress''' once it has been accepted. | *By default, a task's status is changed to '''In progress''' once it has been accepted. | ||
Each [[Processes | process]] has its own [[Creating a status set | status set]], so you can manage the task status once accepted at the process level. | *Each [[Processes | process]] has its own [[Creating a status set | status set]], so you can manage the task status once accepted at the process level. | ||
==Go To== | ==Go To== |
Revision as of 14:35, 9 January 2025
When a task has the status New (task status), it contains Accept and Decline buttons. These buttons allow the assignee to accept or decline the task:
The setting Status assigned to tasks after clicking "Accept" lets you choose the status the task will automatically be transitioned to once it has been accepted.
This setting is located in the upper part of the additional settings for status sets:
Additional information
- By default, a task's status is changed to In progress once it has been accepted.
- Each process has its own status set, so you can manage the task status once accepted at the process level.