The Summary task is a task, the dates of the planned start and completion of which are automatically calculated based on the ones of its subtasks. The one of its beginning is the smallest of the start dates, and the completion date is the largest of the completion dates.
To make the Summary task, it is necessary to note the corresponding sign in the form of creating a new task: