Subprojects are ordinary Planfix projects with the system field Parent project filled in:
'''Subprojects''' are ordinary Planfix [[projects]] with the system field '''Parent project''' filled in:


   
   
Line 8: Line 8:


   
   
When coupled with Project Groups, the purpose of subprojects is to improve the visual understanding of a company's project structure. In a list of projects, subprojects can be displayed as a tree, which helps you visually display how projects are nested under one another:
When coupled with [[Project groups]], the purpose of subprojects is to improve the visual understanding of a company's project structure. In a list of projects, subprojects can be displayed as a tree, which helps you visually display how projects are nested under one another:


   
   

Latest revision as of 06:24, 9 May 2020

Subprojects are ordinary Planfix projects with the system field Parent project filled in:


PIkML9.png


There's no other difference between a subproject and a regular project.


When coupled with Project groups, the purpose of subprojects is to improve the visual understanding of a company's project structure. In a list of projects, subprojects can be displayed as a tree, which helps you visually display how projects are nested under one another:


7d1pMI.png


In theory, you could have as many subprojects in Planfix as you wanted, but in practice companies usually don't have more than 2-3 levels of nesting.